The legal baseline
OSHA requires the exact location of underground installations to be determined by safe and acceptable means as excavation approaches their estimated location. OSHA has addressed hydro vacuum excavation as an acceptable means. State laws add their own rules. Georgia lists hand digging, potholing, soft digging and vacuum excavation inside the tolerance zone. South Carolina's 2026 law allows only approved soft digging in the tolerance zone and requires clearance to be visually confirmed.
What to log at each pothole
- Ticket number, date and crew
- GPS or station location
- Utility type and color of mark, owner if known
- Depth to top and to bottom, horizontal offset from the mark
- Material and size
- Photo of a tape in the hole showing depth
- Planned bore clearance at that point
Want this checked against your actual policies?Send your dec pages and one prime contract. A licensed agent will tell you where you are exposed. Free, no obligation.
Check my coveragePothole before the bore, not after
OSHA's HDD bulletin stresses multiple verification methods before drilling because visibility is limited compared with open excavation. Expose each crossing in the bore path, including laterals you can locate, before the pilot bore gets there.
Sources
- Cabling Installation & Maintenance, CGA 2025 DIRT key findings (Aug 2026)
- OSHA 29 CFR 1926.651, specific excavation requirements
- OSHA interpretation (2003), hydro vacuum excavation as an acceptable means to locate utilities
- OSHA SHIB 03-13-2018, Avoiding underground utilities during horizontal directional drilling
- Georgia 811, Georgia dig law
- South Carolina Code Title 58 Chapter 36
Sources checked 2026-11-19. Laws and forms change. If a source has moved, call us and we will confirm the current rule.