Before the bore
- Ticket. Number, legal start time, expiration, and a work area description that matches the bore path
- White lining. Photos of the premarked path or entry and exit points where required
- Positive response. A screenshot or export showing every operator's status at start time
- Marks. Wide and close photos of every mark and flag, with a tape or scale and a landmark
- Potholes. Location, utility found, depth to top, size and material, with a photo of the tape in the hole
- Bore plan. Planned depth and clearance at each crossing
During the bore
- Locator tracking data for each rod: depth, pitch and position
- Notes when the head approaches a crossing and the clearance observed
- Fluid volumes and pressures, and any returns seen at the surface
Want this checked against your actual policies?Send your dec pages and one prime contract. A licensed agent will tell you where you are exposed. Free, no obligation.
Check my coverageAfter the bore
- As built depth at each crossing, including sewer laterals
- Restoration photos of entry, exit and pothole locations
- File everything by ticket number and keep it for years, not months
Why each piece matters
OSHA's HDD bulletin says to use the state's one call system before drilling and to use multiple identification and verification methods. OSHA's excavation standard requires exact location by safe and acceptable means as work approaches a line. Several states, such as Texas for pipeline tickets, require keeping a record of the positive response. Your records prove you did each step.
Use the free pre bore documentation checklist on site.
Sources
- OSHA SHIB 03-13-2018, Avoiding underground utilities during horizontal directional drilling
- OSHA 29 CFR 1926.651, specific excavation requirements
- Railroad Commission of Texas, 16 TAC 18.5 positive response records
- Cabling Installation & Maintenance, CGA 2025 DIRT key findings (Aug 2026)
Sources checked 2026-11-19. Laws and forms change. If a source has moved, call us and we will confirm the current rule.