Examples from our licensed states
| State | Ticket life |
|---|---|
| Iowa | 25 calendar days from the end of the 48 hour period |
| Illinois | 28 calendar days, then a subsequent notice for another 28 |
| Kentucky | 21 calendar days, remark 2 working days before each period ends |
| Minnesota | 14 calendar days, or 6 months with periodic refresh agreements |
| Tennessee | 15 calendar days from the start date and time |
| South Carolina | 15 working days after the commencement date |
| New Jersey | 45 business days for a routine ticket |
| Pennsylvania | No fixed life, but renotify after leaving the site more than 2 business days |
Every state is on the 811 lookup with sources.
Want this checked against your actual policies?Send your dec pages and one prime contract. A licensed agent will tell you where you are exposed. Free, no obligation.
Check my coveragePractical tips
- Size ticket areas to what the crew will finish before expiration, as North Carolina's law expressly requires
- Track expiration by job on a shared list the foreman checks daily
- Request remarks before marks fade, not after
- Use large project or meet ticket options where the state offers them
Sources
- Cabling Installation & Maintenance, CGA 2025 DIRT key findings (Aug 2026)
- Iowa One Call, Iowa Code Chapter 480
- 220 ILCS 50 (Justia)
- KRS 367.4911
- Minnesota Statutes 216D.04
- Tennessee 811 ticket types
- South Carolina Code Title 58 Chapter 36
- New Jersey One Call FAQ
- 73 P.S. 180
- North Carolina General Statutes Chapter 87 Article 8A
Sources checked 2026-11-19. Laws and forms change. If a source has moved, call us and we will confirm the current rule.