811 notice period and tolerance zone lookup by state

Covers the 26 states where TAKKEL is licensed. Every entry cites the statute or the state's one call center. Where we could not confirm a rule from an official source, we say so instead of guessing.

Full table

StateNoticeTicket lifeTolerance zone
AlabamaAt least 2 but not more than 10 working days before the start, not counting the day of notice (Section 37-15-4(b)).20 working days from the proposed start date. Renew at least 2 working days before it expires if work continues (Section 37-15-4(d)).Width of the facility plus 18 inches on each side of its outside edge, measured horizontally (Section 37-15-2). Use noninvasive methods inside the zone.
ArkansasAt least 2 but not more than 10 full working days before you start (Section 14-271-112).20 working days from the date of notice (Section 14-271-112). Arkansas 811 adds that work must start within 10 working days and the marks must stay visible.18 inches. Inside the approximate location, uncover the facility by a method the operator approves and use no power equipment without the operator's approval (Section 14-271-110).
ConnecticutAt least two full days, not counting Saturdays, Sundays and holidays, and not more than 30 days before excavation (RCSA Section 16-345-4(a)(1)).30 days from the day notice is given, not from the start date. Renewals need two full working days (CBYD).Approximate location is a strip up to 3 feet wide centered on the facility, or up to 1.5 feet on either side of it (CGS Section 16-345).
DelawareNot less than 2 working days and not more than 10 working days before work. The day of the call does not count (Miss Utility).An active ticket does not expire as long as work starts within 10 working days, continues without a break, keeps the same scope and the marks stay visible (Miss Utility, citing Title 26 Chapter 8).24 inches. No mechanized equipment within 24 inches of the marks; hand dig or vacuum excavate inside that zone (Delmarva 811).
GeorgiaThe notice period starts at 7:00 a.m. on the first business day after Georgia 811 gets the request and ends at 7:00 a.m. on a business day at least 2 and not more than 8 business days later (Section 25-9-6(a)).Work must begin no later than 30 calendar days after the ticket's effective date. Work past that needs a new request, which cannot enlarge the original area (Section 25-9-6(c)).Width of the facility plus 18 inches on each side of its outside edge (Section 25-9-3). Inside the zone use hand digging, potholing, soft digging or vacuum excavation unless the owner approves otherwise. Trenchless work carries added duties (Section 25-9-8(d)).
IllinoisNot less than 48 hours and not more than 14 calendar days before the start (Section 4(d)). JULIE tells excavators to plan on calling at least 3 days before digging.A project running past 28 calendar days from the original notice needs a subsequent notice, which is good for another 28 days (Section 4(g)).Approximate location is a strip at least 3 feet wide that extends 1.5 feet on either side of the facility (Sections 2.7 and 2.8). Hand dig or vacuum excavate within 18 inches.
IndianaAt least two full working days before you dig. A ticket submitted after 7:00 a.m. ET does not count that day (Indiana 811).Valid until 11:59 p.m. ET on its expiration date if the marks are undisturbed and visible. Get a new ticket if work will not finish, marks are gone or the location changes (Indiana 811).Two feet on each side of the marks, around the width of the facility. Mechanical equipment only outside the zone, after the line is exposed by hand (Indiana 811).
IowaNotice covers excavation after a 48 hour period that starts at 6:00 a.m. on the next business day after the center gets the notice. Weekends and legal holidays do not count (Sections 480.1 and 480.4(1)(a)).25 calendar days starting the day the 48 hour period ends (Section 480.4(1)(a)).The horizontal location of a facility includes 18 inches on either side of it (Section 480.4(3)(c)).
KansasAt least two full working days but not more than 20 calendar days before the scheduled start (K.S.A. 66-1804, as amended by HB 2226 in 2023).20 calendar days (2023 amendment raised it from 15). The KCC may adjust ticket life by regulation (K.S.A. 66-1804).24 inches from the outside of the facility in all horizontal directions. Water and wastewater operators may elect up to 60 inches (K.S.A. 66-1802, as amended in 2023).
KentuckyNot less than two full working days before work. You may start sooner if every affected operator has marked or cleared (KRS 367.4911(1)).21 calendar days from the initial request. Request remarking two working days before each 21 day period ends (KRS 367.4911(2) and (8)).Width of the facility plus 24 inches on each side (Kentucky 811). Hand dig or use nonintrusive means inside the zone (KRS 367.4911(10)).
LouisianaAt least 48 hours but not more than 120 hours before work, not counting weekends and holidays (R.S. 40:1749.13). Since August 2023 work must also start within 120 hours after the mark by time.Up to 20 calendar days for work that can be finished in that time, or 30 for agricultural, forestry or marine work. Louisiana legislation also defines large project excavation for work that cannot reasonably be finished in that window.18 inches (R.S. 40:1749.14).
MarylandSelect a start date not sooner than 3 business days and not later than 12 business days after the ticket is initiated (PU Section 12-124, as amended in 2022).12 business days after the selected start work date (PU Section 12-124, as amended in 2022).18 inches. Expose the facility by hand or other nondestructive means before using mechanized equipment within 18 inches of a marking (PU Sections 12-126 and 12-127).
MinnesotaAt least 48 hours, not counting the day of notice, Saturdays, Sundays and holidays, and not more than 14 calendar days before excavation (Section 216D.04).14 calendar days from the start time on the notice. Six months if you arrange with the operators to verify or refresh the marks periodically (Section 216D.04).24 inches (Section 216D.04 and 216D.05).
MissouriAt least two working days and not more than ten working days before the expected start date (RSMo 319.026.1). Missouri 811 advises three full working days.Work may continue until the notice's expiration date as long as marks stay visible. If you cannot start within ten working days of the requested date, submit a relocate request first (RSMo 319.026.7).Confirm with Missouri 811
New JerseyWait three business days for a markout on a routine ticket, and begin digging within 10 business days (NJ One Call).45 business days for a routine ticket (NJ One Call).Confirm with New Jersey One Call
North CarolinaNo less than three full working days before the proposed start. Work near a subaqueous facility needs 10 to 20 full working days (G.S. 87-122(a)).Notice expires 28 calendar days after the work start date. The locate area must be one you expect to finish in that time (G.S. 87-122).Half the known diameter plus 24 inches on either side of the centerline, or 24 inches from the outside edge of the mark if the diameter is not marked. For subaqueous facilities, 15 feet on each side (G.S. 87-117(22)).
OhioAt least two working days, not counting the day of notice, and not more than sixteen calendar days before excavation begins (R.C. 3781.28(A)).Confirm with Ohio811 (OUPS)18 inches (R.C. 3781.29). Excavating inside the zone with powered equipment requires a spotter and careful, nondestructive methods (R.C. 3781.30).
OklahomaNot less than 48 hours, not counting the date of notice, Saturdays, Sundays and legal holidays, before excavation (OKIE811 quoting Section 142.6).Notice expires 14 calendar days from the excavation start date. No excavation may continue after that without a new notice (63 O.S. 142.6).Approximate location is a strip two feet on either side of the facility (63 O.S. 142.6).
PennsylvaniaNot less than three and not more than ten business days before excavation (73 P.S. 180).No fixed ticket life. Renotify if you leave the site for more than two business days unless you made other arrangements with the facility owners (73 P.S. 180).The horizontal space within 18 inches of the outside wall or edge of a line (Act 287 definitions). Use prudent techniques such as hand dug test holes or vacuum excavation inside it.
South CarolinaThree to twelve full working days before the start, not counting the day of notice. Work near subaqueous facilities needs ten to twenty working days (Section 58-36-60(A)(1)).Notice expires fifteen working days after the date and time for commencement of work (Section 58-36-60(B)).Half the known diameter plus 24 inches on either side of the centerline, or 24 inches from the outside edge of the mark if the diameter is not marked. Subaqueous: 15 feet each side (Section 58-36-20). Since May 2026 only approved soft digging is allowed in the zone and clearance must be visually confirmed (SC811).
TennesseeAt least three working days and not more than ten working days before the start (T.C.A. 65-31-106, Tennessee 811 ticket types).15 calendar days from the start date and time. To continue, give another notice at least three working days before the fifteenth day ends (T.C.A. 65-31-106).Safety zone at least four feet wide, but not wider than the width of the utility plus two feet on either side (T.C.A. 65-31-108 and TPUC).
TexasAt least two business days (48 hours, not counting weekends and legal holidays) before digging (Texas811).For pipelines under Railroad Commission rules, 14 days unless the excavator and operator agree otherwise in writing (16 TAC 18.1 and 18.3).Chapter 251 sets no general tolerance zone. The One Call Board of Texas points to the 18 inch industry best practice, and Railroad Commission rules set a tolerance zone for pipelines.
VermontAt least 72 hours, not counting Saturdays, Sundays and legal holidays, and not more than 30 days before excavation (30 V.S.A. 7004(c)).Valid until the excavation is not completed within 30 days, the marks fade or are destroyed, or new facilities are installed in the marked area (30 V.S.A. 7004(e)).Approximate location is a strip up to 18 inches on either side of the facility (30 V.S.A. 7001).
VirginiaContact Virginia 811 three working days before digging (Virginia 811).Excavation must begin within thirty working days of the original notification (Code of Virginia 56-265.24(F)).Within two feet on either side of the staked or marked location, take reasonable steps to protect the line. No mechanized equipment within two feet of exposed utility extremities (56-265.24(A)).
West VirginiaNot less than 48 hours, not counting Saturdays, Sundays and legal holidays, and not more than ten work days before the work (W. Va. Code 24C-1-5).Confirm with WV811Operators mark within 24 inches horizontally of the outside walls of the facility (W. Va. Code 24C-1-3).
WisconsinNot less than 3 working days before nonemergency excavation (Section 182.0175(2)(am)1).Give a repeat notice if marks are destroyed or covered, if work does not start within 10 days of the scheduled start, or if work stops for more than 10 days (Section 182.0175(2)(am)4).Keep an estimated minimum clearance of 18 inches between the marking of an unexposed facility and power operated equipment (Section 182.0175(2)(am)5).

Checked November 2026. Rules change; confirm on the ticket and with the one call center before digging. This is not legal advice.

Want a specialist to review your results?

Optional. Your results ride along with the form so we see what you saw. A licensed agent will reply, usually the same business day.

We only use this to respond to you.

Built by people who came from utility construction

Before the next bore, know exactly what your policies will pay for.

Or call 563.321.2430. TAKKEL Insurance, LLC, De Witt, Iowa.

Call 563.321.2430Get a quote