How states define it
North Carolina defines positive response as an automated information system that lets excavators, locators and operators determine the status of a locate request. Operators must respond before the deadline, and excavators must confirm through the system that all operators have responded before digging. South Carolina's 2026 law uses a similar definition and duty.
Indiana requires member utilities to use its positive response system and requires the person responsible for the excavation to acknowledge receipt of the responses before work begins.
When an operator does not respond
- Georgia: if an owner has not responded, the center sends a second request. If there is still no response by noon, the excavator may proceed if there is no visible evidence of an unmarked facility.
- Kentucky: submit a second notice. An excavator who complied is not liable if the operator still fails to respond one working day later.
- Virginia: review and heed the positive response status. If there is clear evidence of an unmarked line, wait three hours after an additional call.
Want this checked against your actual policies?Send your dec pages and one prime contract. A licensed agent will tell you where you are exposed. Free, no obligation.
Check my coverageWhy it matters for insurance
The positive response record shows what the crew knew at start time. It is often the single document that moves a strike from your loss runs to the operator's. Save it with the ticket.
Sources
- North Carolina General Statutes Chapter 87 Article 8A
- South Carolina Code Title 58 Chapter 36
- Indiana 811 professional FAQ
- Georgia 811, Georgia dig law
- KRS 367.4911
- Code of Virginia 56-265.24
Sources checked 2026-11-19. Laws and forms change. If a source has moved, call us and we will confirm the current rule.